The paper considers production scheduling at a single node of a logistics network (waste wood processing facility). Optimization of this node is considered both with single and mulitple objective, one of which is energy minimization.
COBISS.SI-ID: 61491459
This paper considers robust network-level optimization of a waste wood reverse logistics network, and proposes optimal placement of facilities in case of facility failures.
COBISS.SI-ID: 42886915
In this paper an optimal human resource scheduling solution is developed for transportation and logistics. The human resource cost in the management of supply chains is crucial , thus it is also in the focus of the project. A network based method is applied and the efficiency is tested on simulated and real-world data.
COBISS.SI-ID: 26713603